Why divide fixed cost by productive hours instead of attendance hours?
Setup pauses, maintenance, and idle gaps mean spindles and lasers cut fewer hours than attendance; dividing by attendance hours underprices every job.
Does updating a machine rate alter sent quotes?
No. Saving creates a new frozen rate version; existing quotes keep the version used when they were calculated.
Using actual productive hours
$49.65
Using attendance hours
$32.08
Difference per hour
$17.57
Productive hours
1056 h

Breakdown per productive hour

  • Depreciation, maintenance and overhead$13.64
  • Operator allocated$30.30
  • Energy and consumables$5.71

Real utilization sensitivity

UtilizationProductive h/yearActual rate/hGap/h vs attendance
40 %704 h$71.62$39.54
60 %1056 h$49.65$17.57
75 %1320 h$40.86$8.78
90 %1584 h$35.00$2.92

If you price on attendance hours, every productive hour loses the gap shown in red.