How to amortize machine setup time across 1, 10 and 50 units
Pulling stock, loading the program, setting work offsets and inspecting first article takes 45 minutes whether the buyer orders 1 bracket or 50. Separating setup minutes from cycle time stops small rush jobs from draining shop profit.
| Batch qty | Setup / unit | Unit cost | Unit price (40% margin) | Batch total |
|---|---|---|---|---|
| 1 | $61.50 | $81.70 | $136.17 | $136.17 |
| 5 | $12.30 | $32.50 | $54.17 | $270.85 |
| 10 | $6.15 | $26.35 | $43.92 | $439.20 |
| 25 | $2.46 | $22.66 | $37.77 | $944.25 |
| 50 | $1.23 | $21.43 | $35.72 | $1,786.00 |
- Record fixed setup minutes separately from per-piece run minutes on every operation.
- Compute total batch cost at each quantity tier by adding full setup, run time x quantity, and tier material.
- Divide unit cost by (1 - target margin on selling price), round half-up to the cent, and multiply by tier quantity.
- Show 1, 10 and 50 tiers side by side so buyers see why prototypes cost more per piece than production runs.
FAQ
When should we add a minimum order floor on top of setup?
Whenever order entry, packaging and staging make tiny jobs unprofitable even with machine setup billed.
Why is tier total equal to rounded unit price times quantity?
So every line on the customer quote multiplies cleanly with zero penny-rounding discrepancies.